AM Enterprise 2025 Sample Reports


Manufacturing - Production Reports

The Production Reports provide information that is important in planning and managing the inventory item, machine, and/or labor resources. More specifically, these reports provide information on the work orders that are still in process and the estimated quantities of component items and machine or labor resources to complete production.

Each of the Production Reports has various options and criteria that provide a wide variety of work order production-related information and report formats. Read the information below to get a closer look at each of the Production Reports available in the Manufacturing module.

Work in Process Report

The Work in Process Report provides information on work orders that are recorded to work-in-process. The specific information in this report includes the work order numbers, master item numbers and descriptions, request date, transaction date, manufacturing step number, work-in-process quantity, and total cost. This report serves as reference in identifying the outstanding work orders and in monitoring the cost of the work orders posted to work-in-process. It can also be useful in planning and managing the component resources availability.

Click image to enlarge/reduce view

Projected Completion Report

The Projected Completion Report provides information on the work-in-process transactions that are posted in AccountMate but are not yet finished. The report includes details such as the work order numbers, item numbers and descriptions, request dates, work-in-process quantities, start dates, average number of days to finish each work order, and the estimated finished date. This report comes in handy when you need to know the number of days it takes to complete the work orders that are still in process, when you need to assign priority to the work orders for completion, and when you plan the availability of resources needed to complete the work orders.

Click image to enlarge/reduce view

Labor in WIP Report

The Labor in WIP Report provides information on the required manufacturing time of labor components for each work order that is posted to work-in-process. This report displays information such as work order numbers, manufacturing step levels, labor component numbers and names, start dates, work shifts, work-in-process numbers, work types, and manufacturing time used. This report is useful in reviewing and planning the labor resources schedule.

Click image to enlarge/reduce view

Machine in WIP Report

The Machine in WIP Report provides information on the required manufacturing time of machine components for each work order that is posted to work-in-process and when these machine resources are needed. This report displays details such as work order numbers, work-in-process numbers, manufacturing step levels, machine component numbers and descriptions, start dates, work type, and manufacturing time used. This report is useful in reviewing and planning the machine resources schedule.

Click image to enlarge/reduce view

Resource Allocation Report

The Resource Allocation Report provides information on inventory, labor, and machine components that are allocated or reserved for the work orders that are posted to work-in-process. Specifically, this report displays the work order numbers, work-in-process numbers, component numbers and descriptions, start dates, manufacturing step level, work shifts, allocated time, component work-in-process quantities, unit costs, and extended costs pertaining to the components that have been allocated for the work orders in process. This report can be used as reference in identifying the cost of each component in each work order that is in process. It can also help in determining the components' work-in-process quantities and the allocated time of machine and labor resources.

You can choose to generate the report showing only the inventory components, only the machine components, only the labor components, or all components regardless of their types.

Click image to enlarge/reduce view

Scrap Report

The Scrap Report provides information on the scrap quantities from the component items used during the manufacturing process. The report includes work order numbers, job numbers, component item numbers and descriptions, warehouse, finished date, scrap quantities and unit costs, and extended costs of the scrap quantities from the component items used in completing the job. You can use this report in identifying the scrap quantities from the component items used in the process of completing the work order. It is also useful in monitoring and verifying the accuracy of scrap costs.

Click image to enlarge/reduce view